Articles

Management Force has been awarded a contract from DESFA SA, to carry out a Safety Study for the Project “Sidirokastro Border Station Upgrade” according to the provisions of the recently introduced technical regulation about the high pressure (>16 bar)  gas transmission systems (Ministerial Decree ΥΑ Δ3/Α/οικ. 4303 ΠΕ 26510 and its amendment Δ3/Α/8857).

According to the above mentioned legislation, a Quantitative risk assessment - QRA shall be made for all new high pressure gas transmission facilities and projects, in order to check that associated risk is below tolerability criteria.

The QRA for the Project used the OGP criteria for the LOC scenarios and run the BEVI analysis. The TNO QRA software package (Effects and Riskcurves) is used.